The Minister stressed the importance of facilitating the
handover process for beneficiaries, addressing any issues promptly, and
ensuring smooth organization. He also emphasized the need to accelerate
remaining construction works, in order to deliver all pending units across
residential projects.
Engineer Marwa Hussein, Head of the Sheikh Zayed City
Development Authority, stated that units located in the expansion area, as
designated by Presidential Decree No. 230 of 2017, will be delivered as
follows:
Building 145, Sunday, August 3, 2025
Building 144, Wednesday, August 6, 2025
Building 143, Sunday, August 10, 2025
Building 142, Wednesday, August 13, 2025
Building 141, Sunday, August 17, 2025
Building 140, Wednesday, August 20, 2025
Building 112, Sunday, August 24, 2025
Building 113, Wednesday, August 27, 2025
Building 114, Sunday, August 31, 2025
Building 115, Wednesday, September 3, 2025
Building 116, Sunday, September 7, 2025
Building 117, Wednesday, September 10, 2025
Building 118, Sunday, September 14, 2025
Building 119, Wednesday, September 17, 2025
Building 120, Sunday, September 21, 2025
Building 139, Wednesday, September 24, 2025
Building 127, Sunday, September 28, 2025
Building 128, Wednesday, October 1, 2025
Building 135, Sunday, October 5, 2025
Building 137, Wednesday, October 8, 2025
Building 138, Sunday, October 12, 2025
Building 121, Wednesday, October 15, 2025
Building 122, Sunday, October 19, 2025
Building 123, Wednesday, October 22, 2025
Building 124, Sunday, October 26, 2025
Building 125, Wednesday, October 29, 2025
Building 126, Sunday, November 2, 2025
Building 129, Wednesday, November 5, 2025
Building 131, Sunday, November 9, 2025
Building 132, Wednesday, November 12, 2025
Building 133, Sunday, November 16, 2025
Building 134, Wednesday, November 19, 2025
Building 130, Sunday, November 23, 2025
Building 136, Wednesday, November 26, 2025