El-Sherbiny: Handover of 816 units at Janna 4 project starts August 3

فريق رجال الأعمال news 18 July 2025 04:39 PM
مشاركة الخبر:
El-Sherbiny: Handover of 816 units at Janna 4 project starts August 3

Engineer Sherif El Sherbiny, Minister of Housing, Utilities, and Urban Communities, announced that 816 residential units from the Janna Housing Project (Phase 4) in the Sheikh Zayed City Expansion Area will be handed over starting Sunday, August 3, 2025. The delivery will continue on scheduled dates, as announced by the Sheikh Zayed City Development Authority.

The Minister stressed the importance of facilitating the handover process for beneficiaries, addressing any issues promptly, and ensuring smooth organization. He also emphasized the need to accelerate remaining construction works, in order to deliver all pending units across residential projects.

Engineer Marwa Hussein, Head of the Sheikh Zayed City Development Authority, stated that units located in the expansion area, as designated by Presidential Decree No. 230 of 2017, will be delivered as follows:

Building 145, Sunday, August 3, 2025

Building 144, Wednesday, August 6, 2025

Building 143, Sunday, August 10, 2025

Building 142, Wednesday, August 13, 2025

Building 141, Sunday, August 17, 2025

Building 140, Wednesday, August 20, 2025

Building 112, Sunday, August 24, 2025

Building 113, Wednesday, August 27, 2025

Building 114, Sunday, August 31, 2025

Building 115, Wednesday, September 3, 2025

Building 116, Sunday, September 7, 2025

Building 117, Wednesday, September 10, 2025

Building 118, Sunday, September 14, 2025

Building 119, Wednesday, September 17, 2025

Building 120, Sunday, September 21, 2025

Building 139, Wednesday, September 24, 2025

Building 127, Sunday, September 28, 2025

Building 128, Wednesday, October 1, 2025

Building 135, Sunday, October 5, 2025

Building 137, Wednesday, October 8, 2025

Building 138, Sunday, October 12, 2025

Building 121, Wednesday, October 15, 2025

Building 122, Sunday, October 19, 2025

Building 123, Wednesday, October 22, 2025

Building 124, Sunday, October 26, 2025

Building 125, Wednesday, October 29, 2025

Building 126, Sunday, November 2, 2025

Building 129, Wednesday, November 5, 2025

Building 131, Sunday, November 9, 2025

Building 132, Wednesday, November 12, 2025

Building 133, Sunday, November 16, 2025

Building 134, Wednesday, November 19, 2025

Building 130, Sunday, November 23, 2025

Building 136, Wednesday, November 26, 2025